After a six sigma team reached the improve phase of the DMAIC cycle, it was clear that a full redesign of the part was the right path to take. From then on, the DMAIC project became a DFSS project. Which control phase should be used for the newly redesigned part?

🎲 Try a Random Question  |  Total Questions in Quiz: 144  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Six Sigma Black Belt Certification Exam Questions — practice the complete quiz, review flashcards, or try a random question.


After a six sigma team reached the improve phase of the DMAIC cycle, it was clear that a full redesign of the part was the right path to take. From then on, the DMAIC project became a DFSS project. Which control phase should be used for the newly redesigned part?