Subcontractors are required for work at a building site, and two have bid on the job. Subcontractor A will do the job in 16 hours at $133.00/hour and subcontractor B will do the job in 14 hours at $153.00/hour. Subcontractor A has the lower bid.

🎲 Try a Random Question  |  Total Questions in Quiz: 25  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Carpentry Practice Test — practice the complete quiz, review flashcards, or try a random question.

Questions for the Carpentry License Exam.


Subcontractors are required for work at a building site, and two have bid on the job. Subcontractor A will do the job in 16 hours at $133.00/hour and subcontractor B will do the job in 14 hours at $153.00/hour. Subcontractor A has the lower bid.