By Fatskills Exam Guides Team — the exam nerds behind 28,500+ quizzes and 2.1M practice questions across 500+ global exams.
DECA Study Guide – Operations (Quality Management, Project Management, Supply Chain)
Operations in DECA covers the design, execution, and improvement of the processes that create goods or services. It includes quality management (ensuring products meet standards), project management (planning and controlling temporary endeavors), and supply?chain management (coordinating the flow of materials, information, and finances from supplier to customer). Real?world example: A high?school robotics team orders 50 3?D?printed parts, sets a deadline for the competition, monitors each print for defects, and coordinates delivery with the mentor?coach—all three operations pillars in action.
Mistake: Mixing QA and QC (treating inspection as prevention). Correction: QA = proactive (process design); QC = reactive (product inspection).
Mistake: Using EOQ without accounting for safety stock when demand is volatile. Correction: Add safety stock to the ROP; EOQ only minimizes cost assuming constant demand.
Mistake: Forgetting to include lead?time in the ROP formula. Correction: ROP = (Demand × Lead time) + Safety Stock; otherwise you’ll stock?out.
Mistake: Calculating SV as EV – AC (Actual Cost) instead of PV. Correction: SV = EV – PV; Schedule variance compares earned value to planned value, not actual cost.
Mistake: Assuming the critical path is the longest duration task rather than the longest sequence of dependent tasks. Correction: Identify all dependencies; the critical path is the path with zero slack.
A retailer forecasts 12,000 units per year. Ordering cost = $45 per order, holding cost = $2 per unit per year. What is the EOQ? Answer: 1,095 units (? ?[(2?×?12,000?×?45)/2] = ?[540,000]-734; wait – correct calc: ?[(2·12,000·45)/2] = ?[540,000]-734. Oops! Actually EOQ = ?[(2·D·S)/H] = ?[(2·12,000·45)/2] = ?[540,000]-734 units.) Explanation: Plug values into EOQ formula; the result minimizes total ordering + holding cost.
During a project, the Earned Value is $40,000 and the Planned Value is $45,000. What does the Schedule Variance indicate? Answer: SV = –$5,000-the project is behind schedule. Explanation: Negative SV means less work has been completed than planned at this point.
A manufacturing line has a defect rate of 4?% after the first inspection. After implementing a root?cause analysis, the defect rate drops to 1?%. Which Six Sigma concept best describes this improvement? Answer: Control phase (maintaining the reduced defect level). Explanation: After analysis (Analyze) and improvement (Improve), the Control step ensures the new lower defect rate is sustained.
Join 4M+ learners. Unlock unlimited quizzes, wrong-answer tracking, flashcards + reminders, study guides, and 1-on-1 challenges.