By Fatskills Exam Guides Team — the exam nerds behind 28,500+ quizzes and 2.1M practice questions across 500+ global exams.
Project Management Basics cover the planning, execution, monitoring, and closing of a project using standardized tools (e.g., Gantt charts, CPM, Agile sprints). For the FBLA/DECA exam you must demonstrate how to keep a project on?time, on?budget, and aligned with stakeholder goals. Real?world example: A school’s Business?Tech Club launches a “Student?Run E?Commerce Site” – they must define scope, schedule tasks, allocate a $2,500 budget, and report progress to the principal and sponsors.
Mistake: Treating “float” as a buffer you can freely use on any task. Correction: Float only applies to non?critical activities; using it on a critical task creates schedule risk.
Mistake: Confusing EV with PV (students often plug the budgeted total instead of %?complete). Correction: EV reflects work actually performed; calculate it by multiplying the percent complete by the BAC.
Mistake: Ignoring stakeholder communication preferences and sending the same report to everyone. Correction: Use the stakeholder register to tailor frequency, format, and detail level for each audience.
Mistake: Assuming the longest duration path is always the critical path without checking dependencies. Correction: Verify that each activity on the longest path has zero float; any positive float removes it from the critical path.
Mistake: Adding “extra” tasks after the schedule is set and still calling the original timeline the baseline. Correction: Any scope change requires a formal change request and a revised baseline; otherwise the earned?value calculations become invalid.
A project has a BAC of $50,000. After two weeks (40% of the schedule) the team has completed 30% of the work and spent $12,000. What is the Cost Variance (CV)? Answer: CV = EV – AC = (0.30?×?50,000) – 12,000 = $15,000 – 12,000 = $3,000 (under budget).
Which activity is on the critical path?
C) Task C (6 days, float 1) Answer: B) Task B – zero float indicates it lies on the critical path.
In an Agile sprint, the team delivers a usable product increment every 3 weeks. Which statement is true? Answer: The sprint length is a time?boxed iteration, and the team should hold a sprint review and retrospective at the end of each 3?week period.
Join 4M+ learners. Unlock unlimited quizzes, wrong-answer tracking, flashcards + reminders, study guides, and 1-on-1 challenges.