You are troubleshooting a schedule on someone else's computer The schedule has 10,000 tasks. When a change is made to a task's duration on a Fixed Units task, the start and finish dates do not change. change highlighting does not appear, and the Gantt Chart bat does not update. What is the cause of this issue?

🎲 Try a Random Question  |  Total Questions in Quiz: 41  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Microsoft Project Quiz — practice the complete quiz, review flashcards, or try a random question.

Microsoft Project MCQs For LinkedIn Skill Assessments.


You are troubleshooting a schedule on someone else's computer The schedule has 10,000 tasks. When a change is made to a task's duration on a Fixed Units task, the start and finish dates do not change. change highlighting does not appear, and the Gantt Chart bat does not update. What is the cause of this issue?