You are working on a project schedule. You need two tasks to end at the same time so that your review team can do their work on both tasks. Which link type is appropriate?

🎲 Try a Random Question  |  Total Questions in Quiz: 41  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Microsoft Project Quiz — practice the complete quiz, review flashcards, or try a random question.

Microsoft Project MCQs For LinkedIn Skill Assessments.


You are working on a project schedule. You need two tasks to end at the same time so that your review team can do their work on both tasks. Which link type is appropriate?