Matches the outline number initially in Project 2010. It is common for work breakdown structure elements to be numbered sequentially to reveal the hierarchical structure. For example 1.3.2 Rear Wheel identifies this item as a Level 3 WBS element - si

🎲 Try a Random Question  |  Total Questions in Quiz: 54  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Project Management Using Microsoft Project — practice the complete quiz, review flashcards, or try a random question.


1. Matches the outline number initially in Project 2010. It is common for work breakdown structure elements to be numbered sequentially to reveal the hierarchical structure. For example 1.3.2 Rear Wheel identifies this item as a Level 3 WBS element - si