A project was estimated to cost $1.5 million and scheduled to last six months. Halfway through the project, the earned value analysis shows the following: EV = $650,000. PV = $750,000 A. = $800,000. What are the schedule and cost variances?

🎲 Try a Random Question  |  Total Questions in Quiz: 100  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMP: The Monitoring and Controlling Domain — practice the complete quiz, review flashcards, or try a random question.

Includes questions from the following tasks:     Task 1 Measure project performance using appropriate tools and techniques in order to identify and quantify any variances and corrective actions.     Task 2 Manage changes to the project by following the change management plan in order to ensure that project goals remain aligned with business needs.     Task 3 Verify that project deliverables conform to the quality standards established in the quality management plan by using appropriate tools and techniques to meet project requirements and business needs.     Task 4 Monitor and assess risk... Show more

A project was estimated to cost $1.5 million and scheduled to last six months. Halfway through the project, the earned value analysis shows the following: EV = $650,000. PV = $750,000 A. = $800,000. What are the schedule and cost variances?






ADVERTISEMENT