You are halfway through a 12-month project. Your BAC is $12,000. The contractor’s performance to date is PV = $8,000, EV = $7,000, and AC = $9,000. Your SPI = 0.87, and CPI = 0.77. The contractor tells you this is okay because the project still has six months to go, and they can make it up in the last half of the project. This is the first time you have worked with this contractor, so you have no history of past performance. For the contractor to get back to the original due date, the performance level must be:

🎲 Try a Random Question  |  Total Questions in Quiz: 100  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMP: The Monitoring and Controlling Domain — practice the complete quiz, review flashcards, or try a random question.

Includes questions from the following tasks:     Task 1 Measure project performance using appropriate tools and techniques in order to identify and quantify any variances and corrective actions.     Task 2 Manage changes to the project by following the change management plan in order to ensure that project goals remain aligned with business needs.     Task 3 Verify that project deliverables conform to the quality standards established in the quality management plan by using appropriate tools and techniques to meet project requirements and business needs.     Task 4 Monitor and assess risk... Show more

You are halfway through a 12-month project. Your BAC is $12,000. The contractor’s performance to date is PV = $8,000, EV = $7,000, and AC = $9,000. Your SPI = 0.87, and CPI = 0.77. The contractor tells you this is okay because the project still has six months to go, and they can make it up in the last half of the project. This is the first time you have worked with this contractor, so you have no history of past performance. For the contractor to get back to the original due date, the performance level must be:






ADVERTISEMENT