A can do a piece of work in 10 days, B in 15 days. They work together for 5 days, the rest of the work is finished by C in two more days. If they get Rs. 18,000 as wages for the whole work, what are the daily wages of B (in Rs):

🎲 Try a Random Question  |  Total Questions in Quiz: 45  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Time & Work — practice the complete quiz, review flashcards, or try a random question.


A can do a piece of work in 10 days, B in 15 days. They work together for 5 days, the rest of the work is finished by C in two more days. If they get Rs. 18,000 as wages for the whole work, what are the daily wages of B (in Rs):