A Scrum Team works on a project in 2-week Sprints. During the Sprint Planning meeting of the fifteenth Sprint, the Scrum Master says: We have seen from the last 12 Sprints that we cannot deliver potentially shippable increments in 2 weeks. Let's increase the duration for Sprint 16." Should the duration be increased?"

🎲 Try a Random Question  |  Total Questions in Quiz: 186  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Agile Scrum Foundation Certification Prep — practice the complete quiz, review flashcards, or try a random question.


1. A Scrum Team works on a project in 2-week Sprints. During the Sprint Planning meeting of the fifteenth Sprint, the Scrum Master says: We have seen from the last 12 Sprints that we cannot deliver potentially shippable increments in 2 weeks. Let's increase the duration for Sprint 16." Should the duration be increased?"