A Team is transitioning into Scrum. They already had a role called Project coordinator, who facilitates interactions, removes roadblocks and acts as the process coach of the Team. What should this role be called after the transition?

🎲 Try a Random Question  |  Total Questions in Quiz: 186  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Agile Scrum Foundation Certification Prep — practice the complete quiz, review flashcards, or try a random question.


1. A Team is transitioning into Scrum. They already had a role called Project coordinator, who facilitates interactions, removes roadblocks and acts as the process coach of the Team. What should this role be called after the transition?