Use the excerpt below to answer the following question:Refer to the project schedule below to track your progress.Note that any internal revisions will add at least one day to the schedule and any client revisions will add at least two days. Setup2 days (complete Tuesday, January 24) Phase 15 days (complete Tuesday, January 31) Phase 25 days (complete Tuesday, February 7) Phase 34 days (complete Monday, February 13) Closeout1 day (complete Tuesday, February 14) Kierstin ordered the software for the project on January 20, but the shipment was delayed and did not arrive until January 25. The team began setup on the following day. How many days of work will they need to make up to stay on schedule

🎲 Try a Random Question  |  Total Questions in Quiz: 34  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
WorkKeys Assessments: Workplace Documents Practice Test — practice the complete quiz, review flashcards, or try a random question.

The WorkKeys Workplace Documents assessment measures skills that individuals use when they read real workplace documents and use that information to make job-related decisions and solve problems. The documents include messages, emails, letters, directions, signs, bulletins, policies, websites, contracts, and regulations.
 


Use the excerpt below to answer the following question:<br><table border='1' cellpadding='0' cellspacing='0'><tbody><br><tr><br><td>Refer to the project schedule below to track your progress.<br>Note that any internal revisions will add at least one day to the schedule and any client revisions will add at least two days.<br></td><br></tr><br><tr><br><td> <br></td><br></tr><br><tr><br><td> <br></td><br><td><b>Setup</b><br></td><br><td>2 days (complete Tuesday, January 24)<br></td><br><td> <br></td><br></tr><br><tr><br><td> <br></td><br><td><b>Phase 1</b><br></td><br><td>5 days (complete Tuesday, January 31)<br></td><br><td> <br></td><br></tr><br><tr><br><td> <br></td><br><td><b>Phase 2</b><br></td><br><td>5 days (complete Tuesday, February 7)<br></td><br><td> <br></td><br></tr><br><tr><br><td> <br></td><br><td><b>Phase 3</b><br></td><br><td>4 days (complete Monday, February 13)<br></td><br><td> <br></td><br></tr><br><tr><br><td> <br></td><br><td><b>Closeout</b><br></td><br><td>1 day (complete Tuesday, February 14)<br></td><br><td> <br></td><br></tr><br><tr><br><td> <br></td><br><td> <br></td><br><td> <br></td><br><td> <br></td><br></tr><br></tbody></table><br>Kierstin received an email from the client, requesting a revision to Phase 2 that will add 1 day of production work and ½ day of QA/QC. What is the new final completion date