The simulation of the process shown resulted in the message simulation finished but not all tasks were completed successfully. The business analyst believes a terminate node needs to be changed to an end node. Identify the task which should be connected to an end node, assuming no resource contention issues.

🎲 Try a Random Question  |  Total Questions in Quiz: 63  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
IBM Certified Business Process Analyst C9550-606 Exam — practice the complete quiz, review flashcards, or try a random question.


The simulation of the process shown resulted in the message simulation finished but not all tasks were completed successfully. The business analyst believes a terminate node needs to be changed to an end node. Identify the task which should be connected to an end node, assuming no resource contention issues.