Building & Construction Practice Test: PERT & CPM
Fast practice, instant feedback. Timer auto-submits when time’s up.
Avg score: 61% Most missed: “Bar charts were modified later to obtain the milestone charts.”
PERT and CPM are both project management techniques. PERT stands for Project Evaluation and Review Technique, while CPM stands for Critical Path Method.  PERT is a visual technique that helps project managers plan, schedule, and control uncertain activities. PERT focuses on time planning and control, and incorporates three time estimates for each activity: optimistic, pessimistic, and most likely.  CPM is a statistical technique that helps project managers plan, schedule, and control well-defined activities. CPM is used to manage time and cost. CPM relies on a single, deterministic estimate... Show more
Building & Construction Practice Test: PERT & CPM
Time left 00:00
12 Questions

1. The difference between the maximum time available and the actual time needed to perform an activity is known as _________
2. According to the time estimates made by the PERT planners, the maximum time that would be needed to complete an activity is called as __________
3. The full form of CPM is ___________
4. The shortest possible time in which an activity can be achieved under ideal circumstances is known as ________
5. The full form of PERT is ___________
6. Bar charts were modified later to obtain the milestone charts.
7. In bar charts, which colour is used to show the actual progress?
8. Who introduced the bar charts?
9. In a network, a critical path is the time-wise shortest path.
10. Which of the following is not a phase of project management?
11. _________ are used to represent activity in a network diagram.
12. A PERT network is activity-oriented while a CPM network is event-oriented.