Fatskills
Practice. Master. Repeat.
Study Guide: Intro to Project Management: Project Schedule Management - Activity List and Activity, Attributes
Source: https://www.fatskills.com/dsst/chapter/intro-to-project-management-projmgmt-project-schedule-management-activity-list-and-activity-attributes

Intro to Project Management: Project Schedule Management - Activity List and Activity, Attributes

By Fatskills Exam Guides Team — the exam nerds behind 28,500+ quizzes and 2.1M practice questions across 500+ global exams.

⏱️ ~4 min read

What This Is

An activity list is a collection of tasks that need to be performed to complete a project. It's a crucial component of project planning, as it helps project managers create a realistic schedule, allocate resources, and estimate costs. For example, building a new office building requires activities like site preparation, foundation work, framing, electrical and plumbing installation, and finishing work.

Key Terms & Formulas

  • Activity: A specific task or action that needs to be performed to complete a project.
  • Activity Attributes: Characteristics of an activity, such as duration, cost, and resource requirements.
  • Duration: The length of time an activity takes to complete (e.g., 5 days).
  • Predecessor: An activity that must be completed before another activity can start.
  • Successor: An activity that depends on the completion of another activity.
  • Dependency: A relationship between activities where one activity depends on the completion of another.
  • Critical Path: The sequence of activities that determines the minimum duration required to complete a project.
  • Critical Path Method (CPM): A technique used to identify the critical path and calculate the project duration.
  • Program Evaluation and Review Technique (PERT): A method used to estimate activity durations and calculate the project duration.
  • EV = % complete × BAC (Earned Value = percent complete times Budget at Completion).
  • CV = BAC - EV (Cost Variance = Budget at Completion - Earned Value).
  • SV = EV - AC (Schedule Variance = Earned Value - Actual Cost).
  • CPI = EV / AC (Cost Performance Index = Earned Value / Actual Cost).
  • SPI = EV / PV (Schedule Performance Index = Earned Value / Planned Value).

Step-by-Step / Process Flow

  1. Identify Activities: Break down the project scope into smaller, manageable tasks. Use techniques like decomposition, mind mapping, or brainstorming to identify activities.
  2. Estimate Activity Durations: Determine the length of time each activity takes to complete. Use historical data, expert judgment, or statistical methods to estimate activity durations.
  3. Estimate Activity Costs: Calculate the resources required for each activity, including labor, materials, and equipment. Use techniques like bottom-up estimating or parametric estimating to estimate activity costs.
  4. Sequence Activities: Determine the order in which activities need to be performed. Use techniques like critical path method (CPM) or program evaluation and review technique (PERT) to sequence activities.
  5. Identify Dependencies: Determine the relationships between activities, including predecessors and successors.
  6. Create a Schedule: Use the activity list, estimated durations, and dependencies to create a project schedule.

Common Mistakes

  • Mistake: Failing to identify all activities required to complete a project.
  • Correction: Use techniques like decomposition, mind mapping, or brainstorming to ensure all activities are identified.
  • Mistake: Underestimating activity durations or costs.
  • Correction: Use historical data, expert judgment, or statistical methods to estimate activity durations and costs accurately.
  • Mistake: Failing to sequence activities correctly.
  • Correction: Use techniques like CPM or PERT to ensure activities are sequenced correctly.

Exam Tips

  • Tip: Be able to explain the difference between activity and task.
  • Tip: Know how to calculate earned value, cost variance, and schedule variance.
  • Tip: Understand the concept of critical path and how it affects project duration.

Quick Practice Questions

  1. If the CPI is 0.8, is the project under or over budget? Answer: Over budget. Explanation: A CPI of 0.8 indicates that the actual cost is 20% higher than the budgeted cost.
  2. If the EV is $100,000 and the BAC is $200,000, what is the CV? Answer: -$100,000. Explanation: The CV is the difference between the BAC and the EV, which is -$100,000.
  3. If the SPI is 0.9, is the project ahead or behind schedule? Answer: Behind schedule. Explanation: A SPI of 0.9 indicates that the actual cost is 10% higher than the planned value.

Last-Minute Cram Sheet

  • An activity is a specific task or action that needs to be performed to complete a project.
  • Activity attributes include duration, cost, and resource requirements.
  • Predecessor and successor are terms used to describe the relationships between activities.
  • Critical path is the sequence of activities that determines the minimum duration required to complete a project.
  • EV = % complete × BAC (Earned Value = percent complete times Budget at Completion).
  • CV = BAC - EV (Cost Variance = Budget at Completion - Earned Value).
  • SV = EV - AC (Schedule Variance = Earned Value - Actual Cost).
  • CPI = EV / AC (Cost Performance Index = Earned Value / Actual Cost).
  • SPI = EV / PV (Schedule Performance Index = Earned Value / Planned Value).
  • Decomposition breaks down work, not activities – it creates the WBS, not the activity list.
  • Earned value is not the same as actual cost – it's a measure of progress.
  • Schedule variance is not the same as cost variance – it's a measure of schedule performance.