If the project is too large, the people involved should consider reorganizing into multiple cohesive Scrum Teams, each focused on the same product. Therefore, they should share the same Product Objective, Product Backlog, and Product Owner. This statement is

🎲 Try a Random Question  |  Total Questions in Quiz: 67  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Scrum Professional Certificate Exam Practice Test — practice the complete quiz, review flashcards, or try a random question.


If the project is too large, the people involved should consider reorganizing into multiple cohesive Scrum Teams, each focused on the same product. Therefore, they should share the same Product Objective, Product Backlog, and Product Owner. This statement is