Home > Microsoft Project > Quizzes > Microsoft Project Certification Questions 2
Microsoft Project Certification Questions 2
Fast practice, instant feedback. Timer auto-submits when time’s up.
Avg score: 65% Most missed: “Summary Tasks act as:”
Microsoft Project Certification Questions 2
Time left 00:00
25 Questions

1. What is the purpose of the Organizer in the Backstage view?

2. Which element would you utilize in the event that you need to sort tasks by duration and cost?

3. What type of chart is used to display the summary of tasks?

4. What does WBS codes represent?

5. If someone sends a project file from an older version of Project, in Legacy Formats within the Trust center, the best option to select

6. What is the critical path?

7. Which way is NOT a valid method of importing an Excel Workbook into Microsoft Project?

8. When you save a baseline it saves:

9. In MS Project Gantt, Task and Timeline are all examples of what?

10. If using recurring tasks and a project gets delay MS Project will:

11. Why is it not a good idea to have Project create new resources?

12. Which resource would you use to track expenses that aren't based on time or quantity; such as airfare, fees or tuition?

13. The task inspector is good for _______.

14. When the stakeholders approve your project plan, what is the next step in Microsoft Project?

15. Which of these is an example of a project resource?

16. When two tasks overlap using the same resource, what indication appears in the Timeline view?

17. Which type of links is the most commonly used?

18. If using the Team Planner, you can assign and schedule a task by

19. A milestone is a good way to do all except which of the following?

20. What is earned value?

21. In some Gantt chart views, critical tasks are marked in red, and non-critical tasks are marked in blue. What do critical tasks have that makes them different from non-critical tasks?.

22. What does it mean for a task to have a positive cost variance?

23. When tasks overlap, what can you do in Microsoft Project in order to allow resources to finish a short task and then go back to other work?

24. What values determine how Microsoft Project calculates resource assignments?

25. Over allocation is where