Project Management Software Exam Questions
Fast practice, instant feedback. Timer auto-submits when time’s up.
Avg score: 43% Most missed: “When you apply a group to your project schedule, the data in the summary rows ca…”
Project Management Software Exam Questions
Time left 00:00
25 Questions

1. view

2. Changing the appearance of data in a view can make it easier to read and understand project data.

3. If you have two views displayed in a combination view and want to print the view, only the view in the ________ pane will print.

4. A(n) __________ is a way of ordering task or resource information in a view by the criteria you specify.

5. _________ enables you to see on your screen what will print on paper before you print it.

6. In a report, you can only ________ information.

7. In Microsoft Project, you can edit predefined tables but you cannot create new custom tables to suit your needs.

8. In the Print Preview window, the status bar shows '4 rows by 3 columns.' How many pages will be printed?

9. In a view, you can information.

10. If you wanted to print a list of tasks showing start dates, finish dates, and assigned resources, which view might you use?

11. When you apply a filter, you may see gaps in the order of the ________

12. Resource leveling cannot always resolve all resource over allocations.

13. Under allocated

14. Multiple Level Undo can be used

15. You can assign two types of material consumption rates in Microsoft Project.

16. progress bar

17. It is not acceptable to allow a minor over allocation to remain in a schedule.

18. format

19. You must provide Microsoft Project a remaining duration value for it to calculate a percentage complete.

20. You can have up to six cost rate tables for a resource.

21. The only true indicator of project health is whether or not 'the project is on schedule.

22. Resource leveling never changes who is assigned to tasks, or the total work value of those assignments.

23. actual cost

24. A resource cannot have both a cost per use and a cost derived from its pay rate.

25. Planning refers to the collecting, entering, and analyzing of actual project performance data.