You are the project manager of a project. The project plan has been developed. A project end date has been established. The customer later requesters additional work to be included in the project, but will not renegotiate the end date. Cost is not a factor. What should the project team do immediately?

🎲 Try a Random Question  |  Total Questions in Quiz: 594  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMI-002 Exam: CAPM — practice the complete quiz, review flashcards, or try a random question.


You are the project manager of a project. The project plan has been developed. A project end date has been established. The customer later requesters additional work to be included in the project, but will not renegotiate the end date. Cost is not a factor. What should the project team do immediately?