By Fatskills Exam Guides Team — the exam nerds behind 28,500+ quizzes and 2.1M practice questions across 500+ global exams.
Control Risks is a critical aspect of project management that involves identifying, assessing, and mitigating potential risks that could impact project objectives. Effective control of risks ensures that projects are delivered on time, within budget, and to the required quality standards. For instance, consider a construction project where a risk assessment reveals that a potential flood could delay the project. The project manager would implement control measures, such as installing flood barriers or relocating critical equipment, to minimize the risk of flooding and ensure the project stays on track.
If a project has a risk with a likelihood of 0.6 and an impact of $100,000, and the risk is not mitigated, what is the expected monetary value of this risk? Answer: $60,000 (0.6 x $100,000). Explanation: The expected monetary value of a risk is calculated by multiplying its likelihood by its impact.
A project manager is conducting a risk reassessment and identifies a new risk with a likelihood of 0.8 and an impact of $50,000. What should the project manager do next? Answer: Update the risk register to reflect the new risk and its associated likelihood and impact. Explanation: Regular risk reassessments are essential to ensure that the risk management plan remains effective and up-to-date.
If a project has a cost performance index (CPI) of 0.8, what does this indicate about the project's cost performance? Answer: The project is under budget. Explanation: A CPI of 0.8 indicates that the project is spending less than planned, resulting in a cost savings.
Join 4M+ learners. Unlock unlimited quizzes, wrong-answer tracking, flashcards + reminders, study guides, and 1-on-1 challenges.