Fatskills
Practice. Master. Repeat.
Study Guide: Intro to Project Management: Project Risk Management Risk Responses Threats Avoid Transfer Mitigate Accept
Source: https://www.fatskills.com/pmp-project-management-professional/chapter/intro-to-project-management-projmgmt-project-risk-management-risk-responses-threats-avoid-transfer-mitigate-accept

Intro to Project Management: Project Risk Management Risk Responses Threats Avoid Transfer Mitigate Accept

By Fatskills Exam Guides Team — the exam nerds behind 28,500+ quizzes and 2.1M practice questions across 500+ global exams.

⏱️ ~4 min read

What This Is

Risk responses to threats are strategies to minimize or manage potential negative impacts on a project. These responses are crucial for successful project delivery as they help project managers anticipate, prepare for, and mitigate risks. For example, consider building a bridge over a river. A project manager identifies a risk that a flood might damage the bridge during construction. To mitigate this risk, the project manager could plan to build a temporary floodgate or divert the river flow during construction.

Key Terms & Formulas

  • Risk Response Strategy: A plan to minimize or manage a risk.
  • Risk Mitigation: Reducing the likelihood or impact of a risk.
  • Risk Transfer: Shifting the risk to another party, such as through insurance or a contract.
  • Risk Avoidance: Eliminating a risk by not taking a particular action.
  • Risk Acceptance: Deciding to accept a risk and not taking any action to mitigate it.
  • Risk Appetite: The level of risk a project or organization is willing to accept.
  • Risk Tolerance: The level of risk a project or organization can withstand.
  • Risk Threshold: The point at which a risk becomes unacceptable.
  • Risk Probability: The likelihood of a risk occurring.
  • Risk Impact: The potential effect of a risk on the project.
  • Risk Urgency: The time available to respond to a risk.
  • Risk Priority: The relative importance of a risk.
  • Risk Matrix: A tool to categorize risks based on their probability and impact.
  • Expected Monetary Value (EMV) = (Probability × Impact): A formula to calculate the expected value of a risk.

Step-by-Step / Process Flow

  1. Identify risks: Recognize potential threats to the project.
  2. Qualify risks: Assess the likelihood and impact of each risk.
  3. Plan responses: Develop strategies to mitigate, transfer, avoid, or accept each risk.
  4. Implement responses: Put the planned responses into action.
  5. Monitor and review: Continuously assess the effectiveness of the risk responses and update the plan as needed.

Common Mistakes

  • Mistake: Failing to identify all potential risks.
  • Correction: Conduct a thorough risk assessment, including brainstorming sessions and reviews of historical data.
  • Mistake: Not prioritizing risks based on their probability and impact.
  • Correction: Use a risk matrix to categorize risks and focus on the most critical ones.
  • Mistake: Not regularly reviewing and updating the risk management plan.
  • Correction: Schedule regular risk review meetings to ensure the plan remains effective.

Exam Tips

  • Distinguish between risk mitigation and risk transfer: Mitigation reduces the likelihood or impact of a risk, while transfer shifts the risk to another party.
  • Understand the concept of risk appetite: It's the level of risk a project or organization is willing to accept.
  • Be aware of the difference between risk probability and risk impact: Probability is the likelihood of a risk, while impact is the potential effect.

Quick Practice Questions

  1. If a risk has a probability of 0.4 and an impact of $100,000, what is its expected monetary value? Answer: $40,000 (0.4 × $100,000). Explanation: The expected value of the risk is calculated by multiplying the probability by the impact.
  2. A project manager decides to accept a risk with a high probability and significant impact. What is the consequence of this decision? Answer: The project may suffer significant losses if the risk occurs. Explanation: Accepting a risk means not taking any action to mitigate it, which can lead to severe consequences if the risk materializes.
  3. A project manager wants to transfer a risk to a contractor. What should they do? Answer: Include a clause in the contract that shifts the risk to the contractor. Explanation: Transferring a risk involves shifting the responsibility to another party, which can be done through a contract or insurance.

Last-Minute Cram Sheet

  • Risk Response Strategy: A plan to minimize or manage a risk.
  • Risk Mitigation: Reduces the likelihood or impact of a risk.
  • Risk Transfer: Shifts the risk to another party.
  • Risk Avoidance: Eliminates a risk by not taking a particular action.
  • Risk Acceptance: Decides to accept a risk and not take any action to mitigate it.
  • Risk Appetite: The level of risk a project or organization is willing to accept.
  • Risk Tolerance: The level of risk a project or organization can withstand.
  • Risk Threshold: The point at which a risk becomes unacceptable.
  • Risk Probability: The likelihood of a risk occurring.
  • Risk Impact: The potential effect of a risk on the project.
  • Risk Urgency: The time available to respond to a risk.
  • Risk Priority: The relative importance of a risk.
  • Risk Matrix: A tool to categorize risks based on their probability and impact.
  • Expected Monetary Value (EMV) = (Probability × Impact): A formula to calculate the expected value of a risk.
  • ⚠️ Risk Management Plan: A document that outlines the risk management strategy and responses.
  • ⚠️ Risk Register: A document that tracks and monitors risks throughout the project.
  • ⚠️ Risk Assessment: A process to identify, analyze, and prioritize risks.
  • ⚠️ Risk Mitigation Plan: A plan to reduce the likelihood or impact of a risk.


ADVERTISEMENT