By Fatskills Exam Guides Team — the exam nerds behind 28,500+ quizzes and 2.1M practice questions across 500+ global exams.
Project selection methods help organizations choose which projects to pursue, based on their potential benefits and constraints. This is crucial for successful project delivery, as it ensures that resources are allocated effectively and that projects align with strategic objectives. For example, a city planning department must decide whether to build a new bridge, upgrade an existing one, or implement a public transportation system. By using project selection methods, they can evaluate the costs, benefits, and risks of each option and make an informed decision.
If the NPV of a project is $100,000 and the discount rate is 10%, what is the present value of the project's benefits? Answer: $909,091 (NPV = FV / (1 + r)^n, where FV = $100,000, r = 0.10, and n = 1) Explanation: The present value of the project's benefits is $909,091, which is the NPV divided by the discount rate.
If the IRR of a project is 15% and the initial investment is $100,000, what is the payback period? Answer: 6.67 years (PBP = Initial Investment / IRR, where Initial Investment = $100,000 and IRR = 0.15) Explanation: The payback period is 6.67 years, which is the initial investment divided by the IRR.
If the CPI is 0.8, is the project under or over budget? Answer: Over budget (CPI = EV / AC, where EV = $100,000 and AC = $125,000) Explanation: The project is over budget because the actual cost is higher than the planned cost.
Join 4M+ learners. Unlock unlimited quizzes, wrong-answer tracking, flashcards + reminders, study guides, and 1-on-1 challenges.