Fatskills
Practice. Master. Repeat.
Study Guide: Intro to Project Management: Project Schedule Management Developing the Schedule Gantt Chart Network Diagram
Source: https://www.fatskills.com/pmp-project-management-professional/chapter/intro-to-project-management-projmgmt-project-schedule-management-developing-the-schedule-gantt-chart-network-diagram

Intro to Project Management: Project Schedule Management Developing the Schedule Gantt Chart Network Diagram

By Fatskills Exam Guides Team — the exam nerds behind 28,500+ quizzes and 2.1M practice questions across 500+ global exams.

⏱️ ~4 min read

What This Is

Developing the schedule is a critical project management process that involves creating a detailed timeline for project activities. This process ensures that all tasks are completed on time, within budget, and to the required quality standards. For example, when building a new highway, the project manager must develop a schedule that accounts for the construction of bridges, roadways, and interchanges, as well as the installation of traffic signals and utilities.

Key Terms & Formulas

  • Gantt Chart: A graphical representation of a project schedule, showing tasks and their dependencies.
  • Network Diagram (PDM or PERT): A diagram that displays the relationships between tasks and activities, used to plan and schedule projects.
  • Critical Path Method (CPM): A technique used to determine the minimum duration required to complete a project.
  • Critical Path: The sequence of tasks that determines the minimum duration required to complete a project.
  • Earliest Start (ES): The earliest time a task can start.
  • Latest Finish (LF): The latest time a task can finish without delaying the project.
  • Float (Slack): The amount of time a task can be delayed without affecting the project schedule.
  • Dependency: A relationship between tasks that determines the order in which they can be performed.
  • Predecessor: A task that must be completed before another task can start.
  • Successor: A task that depends on the completion of another task.
  • Duration: The amount of time required to complete a task.
  • EV = % complete × BAC (Earned Value = percent complete times Budget at Completion): A formula used to calculate the earned value of a project.
  • CPI = EV / AC (Cost Performance Index = Earned Value / Actual Cost): A formula used to calculate the cost performance index of a project.
  • SPI = EV / PV (Schedule Performance Index = Earned Value / Planned Value): A formula used to calculate the schedule performance index of a project.

Step-by-Step / Process Flow

  1. Create a Work Breakdown Structure (WBS): Break down the project into smaller, manageable tasks and activities.
  2. Develop a Network Diagram: Create a diagram that displays the relationships between tasks and activities.
  3. Estimate Task Durations: Estimate the time required to complete each task.
  4. Determine Dependencies: Identify the relationships between tasks and activities.
  5. Calculate the Critical Path: Determine the sequence of tasks that determines the minimum duration required to complete the project.
  6. Create a Gantt Chart: Create a graphical representation of the project schedule.

Common Mistakes

  • Mistake: Assuming that all tasks have equal importance and priority.
  • Correction: Identify and prioritize tasks based on their impact on the project objectives.
  • Mistake: Failing to account for dependencies and relationships between tasks.
  • Correction: Develop a network diagram and identify dependencies to ensure that tasks are performed in the correct order.
  • Mistake: Not considering the critical path when scheduling tasks.
  • Correction: Identify the critical path and schedule tasks accordingly to ensure that the project is completed on time.

Exam Tips

  • Tip: Be able to explain the difference between a Gantt chart and a network diagram.
  • Tip: Understand the concept of the critical path and how it affects the project schedule.
  • Tip: Be able to calculate the earned value, cost performance index, and schedule performance index.

Quick Practice Questions

  1. If the CPI is 0.8, is the project under or over budget? Answer: Under budget. Explanation: A CPI of 0.8 indicates that the project is earning 80% of its budget, which means it is under budget.
  2. If the EV is $100,000 and the AC is $120,000, what is the CPI? Answer: 0.83. Explanation: CPI = EV / AC = $100,000 / $120,000 = 0.83.
  3. If the SPI is 0.9, is the project ahead or behind schedule? Answer: Ahead of schedule. Explanation: An SPI of 0.9 indicates that the project is earning 90% of its planned value, which means it is ahead of schedule.

Last-Minute Cram Sheet

  • A Gantt chart is a graphical representation of a project schedule.
  • The critical path determines the minimum duration required to complete a project.
  • EV = % complete × BAC.
  • CPI = EV / AC.
  • SPI = EV / PV.
  • ⚠️ The critical path is not the same as the longest path in the network diagram.
  • ⚠️ Float (slack) is the amount of time a task can be delayed without affecting the project schedule.
  • ⚠️ A predecessor is a task that must be completed before another task can start.
  • ⚠️ A successor is a task that depends on the completion of another task.
  • ⚠️ The WBS is a hierarchical decomposition of the project into smaller, manageable tasks and activities.


ADVERTISEMENT