You have been assigned to take over a project that is 60 percent complete according to the schedule. After evaluation, you find that the project is running far behind schedule, and that the project will probably take double the time originally estimated by the previous project manager. However, the sponsor has been told that the project is on schedule. What is the BEST course of action you will take?

🎲 Try a Random Question  |  Total Questions in Quiz: 594  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMI-002 Exam: CAPM — practice the complete quiz, review flashcards, or try a random question.


You have been assigned to take over a project that is 60 percent complete according to the schedule. After evaluation, you find that the project is running far behind schedule, and that the project will probably take double the time originally estimated by the previous project manager. However, the sponsor has been told that the project is on schedule. What is the BEST course of action you will take?