Dave is managing a new project to create a radio-operated model plane. The project budget is set at $200,000 and the project must be completed within six months of the starting date. The initial document authorizing this project and giving Dave the authority to apply organizational resources to the project activities is called _______________.

🎲 Try a Random Question  |  Total Questions in Quiz: 21  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMP Practice Test (New) — practice the complete quiz, review flashcards, or try a random question.

This PMP practice test is based on the 6th edition PMBOK Guide. The PMP Test contains questions from the nine Knowledge Areas in the PMBOK Guide:
Integration Management - Scope Management - Time Management - Cost Management - Quality Management - Resource Management - Communications Management - Risk Management - Procurement Management.

Moreover, the PMP exam also has questions taken from the five Key Process Groups:
Initiating - Planning - Executing - Monitoring and Controlling - Closing.


Dave is managing a new project to create a radio-operated model plane. The project budget is set at $200,000 and the project must be completed within six months of the starting date. The initial document authorizing this project and giving Dave the authority to apply organizational resources to the project activities is called _______________.