Earned Value (EV) for a new operating system design project is calculated at $300,000 and the Actual Cost (AC) is $280,000. The Budget at Completion (BAC) is estimated at $500,000. The project is progressing well from a budgetary point of view, since the CPI value is greater than one. What is the Estimate at Completion (EAC) if the future work of the project is performed at the budgeted rate?

🎲 Try a Random Question  |  Total Questions in Quiz: 21  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMP Practice Test (New) — practice the complete quiz, review flashcards, or try a random question.

This PMP practice test is based on the 6th edition PMBOK Guide. The PMP Test contains questions from the nine Knowledge Areas in the PMBOK Guide:
Integration Management - Scope Management - Time Management - Cost Management - Quality Management - Resource Management - Communications Management - Risk Management - Procurement Management.

Moreover, the PMP exam also has questions taken from the five Key Process Groups:
Initiating - Planning - Executing - Monitoring and Controlling - Closing.


Earned Value (EV) for a new operating system design project is calculated at $300,000 and the Actual Cost (AC) is $280,000. The Budget at Completion (BAC) is estimated at $500,000. The project is progressing well from a budgetary point of view, since the CPI value is greater than one. What is the Estimate at Completion (EAC) if the future work of the project is performed at the budgeted rate?