In a crime prevention software development project for a municipal organization, a steering committee is responsible for approving all deliverables before they are transferred to operations. This steering committee is made up of directors from three different municipal agencies. If the steering committee approves the transfer of deliverables with a 2-1 vote, which of the following statements is correct?

🎲 Try a Random Question  |  Total Questions in Quiz: 21  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMP Practice Test (New) — practice the complete quiz, review flashcards, or try a random question.

This PMP practice test is based on the 6th edition PMBOK Guide. The PMP Test contains questions from the nine Knowledge Areas in the PMBOK Guide:
Integration Management - Scope Management - Time Management - Cost Management - Quality Management - Resource Management - Communications Management - Risk Management - Procurement Management.

Moreover, the PMP exam also has questions taken from the five Key Process Groups:
Initiating - Planning - Executing - Monitoring and Controlling - Closing.


In a crime prevention software development project for a municipal organization, a steering committee is responsible for approving all deliverables before they are transferred to operations. This steering committee is made up of directors from three different municipal agencies. If the steering committee approves the transfer of deliverables with a 2-1 vote, which of the following statements is correct?