You and your team are estimating the duration of the coding/unit testing phase. Your optimistic estimate is 1,200 hours, your most likely estimate is 1,700 hours, and your pessimistic estimate is 2,000 hours. The resource rate is $150 per hour. What is your cost estimate of the coding/unit test phase using the PERT estimating technique?

🎲 Try a Random Question  |  Total Questions in Quiz: 96  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMP: The Planning Domain — practice the complete quiz, review flashcards, or try a random question.

Includes questions from the following tasks:     Task 1 Review and assess detailed project requirements, constraints, and assumptions with stakeholders based on the project charter and lessons learned and by using requirement-gathering techniques in order to establish detailed project deliverables.     Task 2 Develop a scope management plan, based on the approved project scope and using scope management techniques, in order to define, maintain, and manage the scope of the project.     Task 3 Develop the cost management plan based on the project scope, schedule, resources, approved project... Show more

You and your team are estimating the duration of the coding/unit testing phase. Your optimistic estimate is 1,200 hours, your most likely estimate is 1,700 hours, and your pessimistic estimate is 2,000 hours. The resource rate is $150 per hour. What is your cost estimate of the coding/unit test phase using the PERT estimating technique?