You are assigned to manage a new project. Your line manager suggests that you should use a tool to help you plan the new project. She suggests that you use a work breakdown structure (WBS) template. Which of the following is the best description of this tool?

🎲 Try a Random Question  |  Total Questions in Quiz: 96  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMP: The Planning Domain — practice the complete quiz, review flashcards, or try a random question.

Includes questions from the following tasks:     Task 1 Review and assess detailed project requirements, constraints, and assumptions with stakeholders based on the project charter and lessons learned and by using requirement-gathering techniques in order to establish detailed project deliverables.     Task 2 Develop a scope management plan, based on the approved project scope and using scope management techniques, in order to define, maintain, and manage the scope of the project.     Task 3 Develop the cost management plan based on the project scope, schedule, resources, approved project... Show more

You are assigned to manage a new project. Your line manager suggests that you should use a tool to help you plan the new project. She suggests that you use a work breakdown structure (WBS) template. Which of the following is the best description of this tool?