You are the program manager for your organization and are working with Tracy, one of the project managers in your program. Tracy is having some trouble understanding the concept of the critical path in her project's network diagram. Which one of the following is the best definition of the critical path?

🎲 Try a Random Question  |  Total Questions in Quiz: 131  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Program Management Professional (PgMP) Practice Test 2 — practice the complete quiz, review flashcards, or try a random question.


You are the program manager for your organization and are working with Tracy, one of the project managers in your program. Tracy is having some trouble understanding the concept of the critical path in her project's network diagram. Which one of the following is the best definition of the critical path?