You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the schedule performance index (SPI) for this program?

🎲 Try a Random Question  |  Total Questions in Quiz: 131  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
Program Management Professional (PgMP) Practice Test 2 — practice the complete quiz, review flashcards, or try a random question.


You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the schedule performance index (SPI) for this program?