Earned Value (EV) for a new optic radar design project is calculated at $100,000 and the Actual Cost (AC) is $80,000. The Budget at Completion (BAC) is estimated at $200,000. What is the current CPI on this project?

🎲 Try a Random Question  |  Total Questions in Quiz: 21  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMP Practice Test (New) — practice the complete quiz, review flashcards, or try a random question.

This PMP practice test is based on the 6th edition PMBOK Guide. The PMP Test contains questions from the nine Knowledge Areas in the PMBOK Guide:
Integration Management - Scope Management - Time Management - Cost Management - Quality Management - Resource Management - Communications Management - Risk Management - Procurement Management.

Moreover, the PMP exam also has questions taken from the five Key Process Groups:
Initiating - Planning - Executing - Monitoring and Controlling - Closing.


Earned Value (EV) for a new optic radar design project is calculated at $100,000 and the Actual Cost (AC) is $80,000. The Budget at Completion (BAC) is estimated at $200,000. What is the current CPI on this project?