Ryan Systems is in the 3rd week of a 5-week project to consolidate all of its data servers to a central location in its new data center. The amount of money spent on this project to date is approximately $80,000. The planned value for the move as of the 3rd week is $50,000. What is the status of the project at this time? Over budget

🎲 Try a Random Question  |  Total Questions in Quiz: 21  |  🧠 Study this quiz with Flashcards
This question is part of a full practice quiz:
PMP Practice Test (New) — practice the complete quiz, review flashcards, or try a random question.

This PMP practice test is based on the 6th edition PMBOK Guide. The PMP Test contains questions from the nine Knowledge Areas in the PMBOK Guide:
Integration Management - Scope Management - Time Management - Cost Management - Quality Management - Resource Management - Communications Management - Risk Management - Procurement Management.

Moreover, the PMP exam also has questions taken from the five Key Process Groups:
Initiating - Planning - Executing - Monitoring and Controlling - Closing.


Ryan Systems is in the 3rd week of a 5-week project to consolidate all of its data servers to a central location in its new data center. The amount of money spent on this project to date is approximately $80,000. The planned value for the move as of the 3rd week is $50,000. What is the status of the project at this time? Over budget<br><img src='https://www.fatskills.com/images2/Tests/281-385pwide (002).jpg' class='testsimg img-responsive' id='examimg1-147-17' />